SAFETY & SECURITY UPDATES

  • Architect: Huckabee
    Contractor: TBD
    Project Delivery Method: Competitive Sealed Proposals
    Current Phase: Construction
     
    August 28, 2020

    • Fencing construction and shade structures are complete. Project closeout is in progress.

     
    August 7, 2019

    • Fencing construction is complete. Shade structure construction is nearly complete.

     
    July 16, 2019

    • Fencing is being installed.
    • Shade structures are being procured.

     
    July 9, 2019

    • The Board of Trustees approved the AIA G802-2017 Safety and Security Project Construction Materials Testing contract with Huckabee & Associates, Inc.

     
    June 6, 2019

    • The Board of Trustees approved the selection of contractors. The shade structures will be constructed by QA Construction and the fencing will be constructed by Tac Services. The project is transitioning into construction.

     
    May 17, 2019

    • The Board of Trustees approved the contractor rankings for the fencing and shade structure projects. The project is transitioning into construction.

     
    May 9, 2019

    • Bids have been received and the district is currently evaluating the proposals from bidders.

     
    April 5, 2019

    • Construction Documents for Packages 1 & 2 are complete, and the project will release for bidding next week.

     
    March 1, 2019

    • Construction Documents for Packages 1 & 2 are in production.

     
    February 12, 2019

    • KISD Board of Trustees approved the Competitive Sealed Proposals project delivery method.

     
    January 13, 2019

    • Construction Documents for Packages 1 & 2 are in production.

     
    December 13, 2018

    • 50% Construction Documents progress review/page turn with Huckabee and KISD Facilities.

     
    November 30, 2018

    • The design team is hard at work developing the bid documents for the project which includes fencing at every academic campus that doesn’t currently have full perimeter fencing and shade structures at all elementary schools that do not currently have two shade structures.

     
    October 18, 2018

    • Facilities met with Huckabee for safety and security project scope.

     
    October 5, 2018

    • KISD and Huckabee are working together to finalize the scope at each campus.
    • This week, Huckabee visited all 42 campuses slated to receive work and received input from the campus leadership.

     
    September 14, 2018

    • KISD and Huckabee are working together to finalize the scope at each campus.

     
    August 9, 2018

    • The Huckabee design team has delivered updated scope documents for all 45 existing academic campuses to KISD for review and feedback.

     
    July 27, 2018

    • The Huckabee design team is working on scope documents for all 45 existing academic campuses to verify the project details with the district.

     
    July 19, 2018

    • Director of Facilities met with Executive Director of Secondary Schools to discuss high schools’ door security.

     
    July 10, 2018

    • KISD Board of Trustees approved a contract with Huckabee for district wide safety and security upgrades.

     
    June 19, 2018

    • Conference call with Huckabee and Facilities department to discuss Safety and Security project scope and planning.

     
    June 12, 2018

    • KISD Board of Trustees approved Huckabee as the Architect for the district wide safety and security upgrades.
    • KISD Board of Trustees approved Competitive Sealed Proposals as the project delivery method.