- Killeen ISD 2018 Bond
- Accessibility Improvements Updates
ACCESSIBILITY IMPROVEMENTS UPDATES
-
Architect: Huckabee
Architect’s Consultants:
Registered Accessibility Specialist: Accessology
Project Delivery Method: Competitive Sealed Proposal
Current Phase: Construction
August 1, 2021- Monthly Progress Report - Click Here
February 12, 2021
- Project 2 (Packages 3 & 4) is under construction. Minor sitework and interior work is in progress until Summer.
January 8, 2021- Project 2 (Packages 3 & 4) is under construction. Sitework is complete. Interior work is in progress at several campuses.
August 7, 2020- Project 1 (Packages 1 & 2) is under construction. Sitework and interior work are in progress at several campuses. Summer work is near completion.
- Project 1 (Packages 3 & 4) is under construction. Sitework and interior work are in progress at several campuses. Summer work is near completion.
June 5, 2020- Project 2 is under construction. Jobsite setup is in progress.
May 7, 2020- Project 2 is on budget. Contractor selection will be presented to the Board on May 12th.
April 16, 2020- Project 1 is under construction. Sitework is in process at 4 campuses.
- Project 2 is currently bidding.
March 20, 2020- Construction Documents for Project 2 (Packages 3 & 4) are complete. The project is transitioning into the bidding phase.
March 13, 2020- Construction Documents for Project 2 (Packages 3 & 4) are in process.
January 30, 2020- Packages 1 & 2 have been brought into budget. The project is transitioning into construction.
January 10, 2020- Cost evaluation is on-going for Packages 1 & 2.
- Construction Documents for Packages 3 & 4 are in process.
July 26, 2019- Construction Documents for Packages 1 & 2 are in production.
March 1, 2019- Design Development documents for Packages 1 & 2 are in production.
January 13, 2019- Design Development documents for Packages 1 & 2 are in production.
December 13, 2018- 50% Construction Documents progress review/page turn with Huckabee and KISD Facilities.
November 30, 2018- KISD has refined the list of potential items to be addressed within the bond budget. The design team is working on outlining the road map for the project moving forward.
October 23, 2018- KISD Board of Trustees received District Accessibility Renovations assessment overview.
September 28, 2018- Huckabee team has completed the organization of the information received from the Registered Accessibility Specialist and delivered a draft of the spreadsheet containing all of the data to KISD. The district is currently reviewing the list of potential project scope items and prioritizing them to determine how the budget funds will be spent.
September 20, 2018- Facilities met with Huckabee for ADA project review.
September 18, 2018- The Board approved Competitive Sealed Proposal as the project delivery method.
September 7, 2018- Accessology has completed their field work and reports.
- Huckabee team is nearly complete with generating solutions for deficiencies and related cost estimating.
August 9, 2018- Huckabee team continues to work through developing solutions for deficiencies and related cost estimating.
August 2, 2018- Accessology continues their assessments of the campuses in the district. To date, they have the field work on 20 campuses complete.
- Huckabee team has begun the effort of determining design solutions to the deficiencies noted in the assessments and estimating cost for those solutions.
July 27, 2018- Accessology, a Registered Accessibility Specialist firm, has teams doing on site assessments of multiple campuses in the district. To date, they have the field work on 11 campuses complete.
- Huckabee team is organizing information received from Accessology and beginning the process of generating solutions to the deficiencies identified in the assessments as well as estimating the potential cost of these solutions.
July 10, 2018- KISD Board of Trustees approved a contract with Huckabee for Accessibility improvements district-wide.
June 19, 2018- Conference call with Huckabee and Facilities department to discuss ADA project scope and planning.
June 12, 2018- KISD Board of Trustees approved Huckabee as the Architect.