KILLEEN HIGH SCHOOL RENOVATION UPDATES

  • Architect: PBK Architects
    Architect’s Consultants:
    Civil Engineering: Cunningham Allen
    MEP Engineering: LEAF Engineers
    Structural Engineering: Dunaway Associates
    Sports Venue Design: PBK Sports
    Landscape Architect: Coleman & Associates
    Technology: LEAF Engineers
    Food Service: FDP
    Building Envelope: BEAM Professionals
    Theater: Teqniqal Systems, LLC
    Acoustical: BAI
    Construction Manager: American Constructors
    Project Delivery Method: Construction Manager at Risk
    Geotechnical Engineer: Langerman Foster Engineering
    Commissioning Agent: DBR Engineering
    Current Phase: Construction
     
    May 28, 2021

    • Steel erection for Fine Arts corridor entry has started.

     
    May 21, 2021

    • KISD approved color options for weight rooms flooring.
    • Paving at loading dock in progress.

     
    May 7, 2021

    • KISD confirmed Bistro name.
    • American Constructors poured slab for Fine Arts.

     
    February 26, 2021

    • Killeen High School construction site was closed from 02/15-02/19 due to inclement weather.
    • Roof installation will resume above Kitchen.

     
    February 12, 2021

    • Frame door installation continues in Kitchen area.
    • Fireproof spray application continues in second floor.

     
    February 5, 2021

    • Langerman Foster sent density reports.
    • Piping installation in progress for Kitchen area.

     
    December 15, 2020

    • City of Killeen sent PBK approved permits for Phase II today.

     
    December 8, 2020

    • GMP 2 was approved by KISD Board of Trustees.

     
    November 13, 2020

    • PBK sent KISD updated renderings.
    • Masonry installation has begun in courtyard #1.

     
    October 16, 2020

    • PBK, American Constructors, and KISD leadership members had in-progress tour to see finished summer construction work today.

     
    October 9, 2020

    • Steel erection for new main entry has begun.
    • Structural steel in new corridor connecting Admin area with classroom wing work in progress.

     
    October 2, 2020

    • American Constructors held Phase II bid process.
    • Installation of underground storm sewer line in progress.
    • New corridor to connect admin area with classroom wing in progress.
    • Grade beams and site work in progress.

     
    September 25, 2020

    • PBK sent additional dimensions for KISD to review clearance between baseball bleachers and existing concession building.
    • Cunningham Allen submitted drawings to the City of Killeen to obtain LD permit.

     
    September 11, 2020

    • PBK sent observation report today.
    • KISD sent PBK new volleyball floor mount specifications to be considered per teachers request.

     
    September 4, 2020

    • KISD asked for additional temporary canopy at true north of Gym, which will be installed next week.
    • Placing furniture in SPED classrooms has started.
    • Finished underground plumbing for classroom wing and cafeteria.

     
    August 28, 2020

    • KISD approved overall floor finish today.
    • New main entry is complete for admin offices.
    • Temporary irrigation for courtyard #2 has been installed.

     
    August 14, 2020

    • PBK sent Observation report - Phase I
    • Langerman Foster Engineering sent moisture density report.
    • Metal wall panel installation at exterior wall next to Auditorium is complete.

     
    August 12, 2020

    • American Constructors started to drill piers.

     
    August 7, 2020

    • New parking layout for main entrance.
    • Casework installation took place in Choir room.
    • Floor installation in progress in Auditorium main entry.

     
    July 31, 2020

    • PBK and KISD received TDLR Plan Review report.
    • KISD held their moving coordination meeting.
    • Installation of lay-in ceiling started in library.

     
    July 24, 2020

    • American Constructors sent KISD schedule plan showing corridors.
    • PBK sent revised fine arts entry to KISD and American Constructors for review.
    • Storefront installation occurred at library.

     
    July 12, 2020

    • Langerman Foster Engineering Company sent concrete reports.
    • Installation of ceiling grid continues.
    • Installation of natural stone at Auditorium entry is underway.

     
    July 10, 2020

    • American Constructors picked up and paid the mobile kitchen permit fee.
    • Langerman Foster Engineering Company sent concrete cylinder test report, field density report, and seven day result for west paving area today to KISD, American Constructors, and PBK.
    • Finished with demolition of classroom wing for new cafeteria and kitchen.

     
    July 02, 2020

    • City of Killeen approved the mobile kitchen permit.
    • PBK sent observation report.

     
    June 26, 2020

    • Langerman Foster Engineering Company sent Field inspection and concrete reports to KISD, American Constructors and PBK.

     
    June 26, 2020

    • Langerman Foster Engineering Company sent Field inspection and concrete reports to KISD, American Constructors and PBK.
    • PBK sent observation report for construction Phase I.
    • Windows are being installed in new library.

     
    June 19, 2020

    • American Constructors sent updated project schedule to KISD and PBK.
    • American Constructors sent Value Engineering log to PBK and KISD.
    • Exterior demolition in process for new cafeteria and new wing classrooms.
    • Interior walls in progrtess for new face of Auditorium entry. 

     
    June 11, 2020

    • City of Killeen informed PBK that kitchen permit is approved.

     
    June 9, 2020

    • Langerman Foster Engineering Company sent their Concrete Cylinder Test report, Moisture density report, and Reinforcing Steel Visual Observation report to KISD, American Constructors, and PBK.

     
    June 5, 2020

    • PBK met with consultants for 95% Construction Documents Page turn review.
    • PBK sent updated technology drawings for Phase II for KISD review.

     
    May 29, 2020

    • PBK sent observation report for construction Phase I today.
    • American Constructors is getting revised budget estimate with VE proposed items and have it ready by mid to late next week.
    • Langerman Foster Engineering Company sent their drilled shaft engineering observation report.

     
    May 15, 2020

    • KISD sent originally fully executed easement document to Oncor.
    • PBK and American Constructors met today to discuss possible VE items.
    • KISD gave approval for stone and block samples.

     
    May 5, 2020

    • KISD sent originally fully executed easement document to Oncor.
    • PBK sent updated composite floor plans per KISD request.

     
    May 1, 2020

    • PBK sent documents to the City of Killeen for kitchen permit.
    • KISD confirmed no issues with door hardware submittal.

     
    April 24, 2020

    • PBK sent KISD a revised Baseball bleachers’ exhibit today for district’s review.
    • City of Killeen confirmed that the permits for Killeen HS Renovation and Modernization were approved without the need to abide the landscape requirements due to the 30% rule. 

     
    April 17, 2020

    • PBK, American Constructors, and KISD met today to review mockup wall, maroon color selection and other finishes.
    • PBK sent renderings to KISD to finalize library shelving color.
    • KISD sent PBK comments regarding access control devices and network data for Phase II.

     
    April 10, 2020

    • American Constructors proposed to eliminate the second fire riser designed for Phase II, which has been approved after being reviewed by LEAF and PBK.
    • PBK, American Constructors and KISD had 75% CD progress set page turn review with consultants on 04/07/2020 and on 04/08/2020 for Architectural.
    • Coleman Associates waiting confirmation from City of Killeen stating that Phase II will not need to abide by landscape requirements, since we will be under the 30% of new construction on site.
    • American Constructors painted a wall with colors selected by KISD to be reviewed and select final maroon color next week.
    • KISD started the process of moving out from KHS Library due to the district closure and give the contractor extra time to complete that portion of work.

     
    April 06, 2020

    • American Constructors sent estimates and clarifications for the 75% CD set of documents.
    • PBK sent American Constructors 90% CD review set for Phase II.
    • PBK sent proposed graphic locations to KISD.

     
    March 27, 2020

    • PBK, American Constructors and KISD will be meeting today to re=select a brick color due to waiting lead times and meet construction schedule.
    • PBK sent CPR 02 which included the changes coordinated with KISD for the library.
    • City of Killeen confirmed they will not require permitting for propane tank.
    • Cunningham Allen sent drainage information for the City of Killeen to finalize plans for LDP application submittal for Phase II.
    • City of Austin issued a shelter in place on 03/24/20. PBK abides with this order, however their staff will continue working from home causing no workload disruption.

     
    March 20, 2020

    • KISD asked PBK to submit portables permit today.
    • PBK, American Constructors and KISD met on 3/18/20 to review hardware for Phase I.
    • KISD confirmed to have white switches, outlets and face plates on 03/17/20.

     
    March 16, 2020

    • PBK sent KISD updated renderings today.
    • KISD approved floor layout for the library. 

     
    March 6, 2020

    • PBK sent Electrical drawings to KISD for mobile kitchen. Water and sanitary drawings from civil are pending.
    • American Constructors provided pricing for Library floor change from carpet to LVT per principal’s request, which KISD approved.

     
    March 4, 2020

    • KISD sent PBK signed GMP 1.
    • PBK sent KISD updated renderings.
    • American Constructors stamped Renovation set of drawings and permit up from City of Killeen.

     
    March 2, 2020

    • KISD approved PBK’s proposed location of the propane tank required to service temporary kitchen.
    • KISD approved the construction sign sent by PBK.
    • KISD and PBK reviewed finished for Phase I and Athletics Revisions and Base Bid options for Phase II on 02/28/20 with campus staff.

     
    February 26, 2020

    • PBK issued CPR 01.
    • American Constructors getting pricing for Library floor change from carpet to LVT per KHS principal’s request.
    • PBK will send KISD site plan drawings for the mobile kitchen to submit for permitting by 03/3/2020.
    • KISD and American Constructors coordinated library furniture and will proceed with Indeco sales. PBK will review submittal.
    • American Constructors showed PBK and KISD mock-up casework which had a few minor items to correct.
    • Cunningham Allen, PBK and American Constructors had a Pre-Development Meeting at the city to discuss Phase II site permitting and drainage/detention items.

     
    February 25, 2020

    • KISD Board of Trustees approved GMP 1.
    • American Constructors sent preliminary submittals for the library casework to KISD for their review.
    • PBK sent KISD Area B – CAD file and paint, carpet, and color samples for their meeting with Perry’s Office Plus.

     
    February 20, 2020

    • PBK sent KISD updated renderings today.
    • KISD proposed to include painting existing gym as an alternate, and address it through KISD annual life cycle painting projects if needed.
    • Cunningham Allen scheduled a Pre-Development Meeting at the city to discuss Phase II site permitting and drainage/detention items for Wednesday 02/26/2020.

     
    February 17, 2020

    • LEAF and PBK were on site investigation today.

     
    February 14, 2020

    • Killeen High School Memorabilia Review Meeting was held and few minor changes were made to Area A. PBK will issue CPR 01 to American Constructors.

     
    February 06, 2020

    • American Constructors sent KISD GMP 1 today.
    • PBK, American Constructors, and KISD had Phase II DD review meetings with department representatives on 2/04/2020.
    • PBK, American Constructors, and KISD has final VE meeting on 02/03/2020.

     
    January 31, 2020

    • PBK, American Constructors, and KISD move out/move in meeting took place today, to finalize details at the start of construction in Spring Break.
    • PBK sent KISD revisions to Phase II 15 Portable permit plan and application on 01/30/2020.

     
    January 24, 2020

    • PBK submitted post-bid Addendum No. 4 to American Constructors.
    • American Constructors submitted GMP 1 to PBK for review.
    • PBK and American Constructors will meet on 01/27/2020 to review potential GMP 1 cost saving items to recommend.

     
    January 21, 2020

    • PBK provided KISD CAD files for furniture vendor to provide renditions.
    • Cunningham- Allen submitted LDP application packet to the City of Killeen.

     
    January 17, 2020

    • American Constructors will have GMP 1 ready for KISD to review on 01/29/20.
    • PBK received comments from the City of Killeen regarding Renovation and Addition building permits and submitted corrections today.
    • PBK and American Constructors agreed to proceed with the original design for the library wall due to timeline concerns.

     
    January 15, 2020

    • PBK paid the LDP application fee to the City of Killeen today, and Cunningham-Allen will be submitting the application packet early next week.
    • PBK met with Dr. Herrera from KISD today for final approval for the art wing. There were a few changes that have been incorporated into the Construction Documents, including the under-mount system vent for the kilns and will coordinate with American Constructors.

     
    January 10, 2020

    • PBK submitted post-bid Addendum No. 3 to American Constructors today.
    • PBK sent KISD Phase II Portables layout today.
    • PBK provided KISD, FFE and Technology budgets from PBK’s two recently completed high school projects, as a guide for the district to finalize their budget.

     
    December 20, 2019

    • PBK will send American Constructors a preliminary Phase II plan set today, to refine budget for both phases.
    • KISD confirmed that students will return Monday 08/17/20, which will reduce summer construction original schedule by 5 days.
    • PBK will provide KISD most recent PBK’s FFE and Technology school estimate, as a guide for the district to finalize their budget.
    • PBK waiting for comments from the city of Killeen regarding Renovation and Addition building permits.

     
    December 18, 2019

    • Phase I Bid Day occurred today.
    • American Constructors refining final numbers from Bid Budget.

     
    December 13, 2019

    • PBK started working on construction documents for Killeen HS Renovations + Modernization- Phase II.
    • PBK, American Constructors, and KISD attended Move in/out coordination meeting No.3 on 12/6/19 to fine tune details.

     
    December 6, 2019

    • PBK issued Addenda No. 2 today.
    • PBK will resubmit split permit sets, per city requirements as Killeen HS Renovation and Killeen HS Addition on 12/09/19.
    • PBK and American Constructors met on 12/05/19 to review Demolition plans. Minor modifications will be issued in a post-bid addendum.
    • KISD will submit site plan for permitting of second round of portables.
    • Pre-bid walk through occurred on Saturday 11/23/19 and 11/26/19.
    • Phase I Bid Day scheduled for 12/18/19.

     
    November 22, 2019

    • PBK will submit plans to the city for permit purposes early next week.
    • PBK working on options to simplify construction of the library existing wall facing the courtyard.
    • PBK issued Addenda No.1 on 11/18/19.
    • PBK is generating site plan for permitting second round of portables.
    • LEAF previously provided project information to ONCOR for service. The y will follow-up early next week.

     
    November 1, 2019

    • PBK sent 100% Issue for Proposal set and specifications on 10/31/2019.
    • PBK and American Constructors will coordinate Addenda schedule and timeline for Phase II.
    • KISD will send comments regarding WAP from district to PBK, which will be incorporated in Addenda.
    • PBK finalizing portable locations incorporating Fire Marshall comments.
    • KISD Safety & Security team review the security camera placements on 10/29/2019 and comments were incorporated in the drawings.
    • PBK met with KISD Superintendent and leadership team to finalize selection of interior finishes on 10/23/2019.

     
    October 11, 2019

    • PBK will meet with KISD for 90% Review page turn today.
    • KISD will provide feedback to PBK for the 19 portables relocation.
    • PBK sent portable permit exhibits on 10/10/2019.

     
    October 04, 2019

    • PBK sent site plan with revised mobile kitchen and ramps today.
    • KISD provided underground fiber location plan to PBK and American Constructors on 10/02/2019.
    • PBK met on 09/30/2019 to review finishes election.
    • PBK delivered a hard copy of 90% Construction Documents Progress Set on 09/30/2019.

     
    September 27, 2019

    • PBK sent PDF’s pf 90% Construction Documents Progress Set today and will deliver a hard copy on 09/30/2019.
    • Coordination meeting was held yesterday to discuss Admin/campus move out plan, during spring break and summer of 2020 with KISD leadership, PBK and American Constructors. PBK to provide revised site plan.
    • PBK to generate portable site plans for City permit.
    • American Constructors will install fire alarm panel and connect to the portables and KISD will provide power to them. 

     
    September 13, 2019

    • PBK and LEAF meeting with KISD to discuss fire alarm design today.
    • PBK and American Constructors met on Wednesday 09/11/2019 to coordinate move out/move in logistics.
    • KISD to determine by end of this month if Nolan Middle School will be used as a swing campus.
    • American Constructors to provide a barrier plan/construction fencing at building interior during construction.

     
    August 30, 2019

    • PBK will provide KISD temporary cafeteria seating capacity at the auxiliary gym and provide for covered walkway to mobile kitchen at todays’ meeting.
    • PBK sent 75% Construction Documents Review set yesterday to KISD and American Constructors.
    • PBK sent KISD list of site plans for district to review.

     
    August 13, 2019

    • KISD Board of Trustees approved the Task Request with DBR Engineering Consultants Inc.

     
    August 9, 2019

    • PBK will submit a draft scheme for portable locations today 08/09/2019.

     
    August 2, 2019

    • PBK and American Constructors are reviewing building separation areas and building construction type.
    • PBK, LEAF, and American Constructors met with KISD to discuss VRF on 07/31/2019. LEAF and American Constructors will provide a list of nearby projects where this system has been implemented.
    • PBK provided 2 option exhibits for temporary kitchen layout implementing vendor requirements on 07/31/2019.
    • PBK received final version of the Geotechnical Report on 07/26/2019.
    • PBK is working on a new exhibit layout of portables to support Library and restrooms. Add 6 Admin portables located by the Band area, which may encroach student parking lot. 

     
    July 26, 2019

    • American Constructors and PBK are working on a construction logistics plan for the Summer of 2020 and the second year of 2020-2021.
    • KISD scheduled a meeting to discuss VRF with Maintenance on Wednesday 7/31/2019 where LEAF and American Constructors will be attending.
    • 50% Architectural Construction Document’s page turn re-scheduled for Tuesday 07/30/2019.

     
    July 19, 2019

    • 50% Construction Document page turn with Food Service and MEPT consultants.

     
    July 12, 2019

    • BEAM site visit to Killeen High School to confirm existing roof conditions above Auditorium and Stage to finalize design for roof plan and drainage.

     
    June 28, 2019

    • PBK met with consultants Wednesday 6/26/2019 and Thursday 6/27/2019 for internal consultant review meeting.

    ·       American Constructors was on-site at Killeen HS Monday 06/24/19 and Tuesday 06/25/19 to chase existing storm and sewer lines. Tim S. identified existing domestic water routing and provided a water shut off plan to PBK on 06/26/19.
    June 24, 2019

    • American Constructors two-day site visit to Killeen High School to locate existing utilities, including storm and sewer lines.

     
    June 05, 2019

    • PBK meeting with KISD School Nutrition to discuss and review mobile kitchen facility. PBK to develop deliverables to be included with Request for Proposals from mobile kitchen vendors.

     
     
     
    May 31, 2019

    • FDP (Food Service) is awaiting answers regarding the Bistro Area from KISD School Nutrition.
    • PBK is working on a proposed relocation layout of IDF racks currently in the Choir area. Racks will not be located on a mezzanine.

     
    May 29, 2019

    • KISD, PBK and Cunningham Allen met with City of Killeen to review the current project status. Platting is not required; site was platted in 1987. A Land Disturbance Permit will be required.

     
    May 23, 2019

    • PBK, BEAM and American Constructors met regarding roofing scope and phasing.

     
    May 9, 2019

    • PBK met with JROTC and Choir departments to review layouts and finishes.
    • PBK met with Technology Services to review IDF and Technology phasing.

     
    May 2, 2019

    • Geotech drilling is complete; Lab work is expected to be completed by May 15th; Final report due May 20th.
    • Part of Special Education scope will be moved to GMP 1.

     
    April 18, 2019

    • Review meetings with PBK and all departments were held at Killeen High school.
    • Due to site drainage, Civil Engineer recommends raising new classroom addition and cafeteria two feet. Next milestone date will be pushed back to incorporate the change.

     
    April 12, 2019

    • PBK and FDP met with KISD stakeholders to discuss temporary kitchen requirements.
    • PBK, BEAM, and American Constructors coordinating best roof options. American Constructors to provide budget estimate comparison between lightweight insulated concrete and Polyiso systems.
    • Architect and Engineering team working towards 50% review set due April 26. One full size set to be provided to KISD and page turn review session to be scheduled.

     
    April 9, 2019

    • KISD Board of Trustees approved AIA B101-2017 contract with Langerman Foster Engineering Company, LLC for Geotechnical Engineering and Materials Testing services.

    April 5, 2019

    • Meeting with KISD Purchasing for mobile kitchen presentation.

     
    March 29, 2019

    • BEAM requesting budget estimates from roofers for recommended roofing options.

     
    March 22, 2019

    • Existing roof coring occurred on 3/14/2019. Fastener pull test by OMG Roofing was received on 3/20/2019.
    • Received Building Envelope Observation report from BEAM.
    • PBK provided KISD with proposed temporary cafeteria seating capacities at interior and exterior locations around the Auxiliary gym.

     
    March 21, 2019

    • PBK met with George De Winne (FDP) to discuss options for the temporary kitchen. A meeting with district food service will be requested. Also need to discuss requirements for the Snack Bar area.

     
    March 15, 2019

    • Existing roof coring occurred on 3/14/2019. 11 cores taken at high and low roofs. Report will be issued the week of 3/18/19
    • American Constructors on site week of 3/11/19 to do preconstruction investigation to include roof sampling, camera work at existing sanitary lines and locating existing utility services within project scope.
    • Geotechnical proposal from Langerman Foster submitted 3/12/19 to KISD.
    • Construction Document review set compiled on 3/7/19.

    March 14, 2019

    • Topographic Survey received from Cunningham Allen.

    March 5, 2019

    • KISD Board of Trustees approved the proposed Schematic Design with alternates for Field House and Fine Arts additions.
    •  

    February 24, 2019

    • School Nutrition design review meeting with PBK and KISD Facilities.

     
    February 15, 2019

    • American Constructors provided cost estimate with alternates for Fine Arts and Athletics for District review.
    • PBK revising renderings.
    • Design and Construction schedule will be revised to indicate Killeen High School GMP 1 is received after KISD HS #6 total GMP is approved.
    • Technology plan review with KISD Facilities and Telecommunications

     
    February 12, 2019

    • KISD Board of Trustees approved DBR as the commissioning agent for Killeen HS Renovation.

     
    February 8, 2019

    • American Constructors reviewing cost estimate with alternates for Fine Arts and Athletics.
    • Structural & MEP consultants site visit scheduled for Monday 02/18/2019.

     
    January 25, 2019

    • Revising kitchen layout to align with High School #6 design.
    • Food Service consultant to incorporate “Bistro” as a fifth serving line.

     
    January 18, 2019

    • Additional field investigation scheduled for Monday 01/21/2019.
    • Geotechnical services to commence pending Board of Trustees approval of Schematic Design presentation.

     
    January 9, 2019

    • Meeting for project asbestos reporting with Burcham Environments, PBK, American Constructors and KISD Facilities.

     
    January 4, 2019

    • Langerman Foster Engineering submitted proposal to KISD for Geotechnical Engineering services for review.
    • PBK revising Floor Plans per Design Development meeting on Friday 12/14/2018.

     
    December 21, 2018

    • PBK coordinating Geotechnical Engineering proposal with Langerman Foster Engineering.
    • PBK revising Athletics area per Design Development meeting on Friday 12/14/2018.
    • PBK revising Choir area per Design Development meeting on Friday 12/14/2018.

     
    December 7, 2018

    • Schematic Design presentation submitted on Thursday 12/6/2018
    • PBK requesting Geotechnical Engineering proposal.
    • PBK developing exhibits for Design Development meeting on Friday 12/14/2018
    • PBK requesting Topographic survey proposal from Cunningham Allen.

     
    November 30, 2018

    • Revising Schematic Design presentation as per comments from Board Workshop.
    • Revising Schematic Design animation as per comments from Board Workshop.
    • Scheduling Design Development meeting for Friday 12/14/2018
    • Setting up Construction Documents to reflect 2 GMP’s.

     
    November 27, 2018

    • Campus meeting with PBK, KISD Facilities and Principal to discuss renovation plans.

     
    November 16, 2018

    • Sent Schematic Design presentation to KISD for review.
    • Sent updated animation to KISD for review.
    • Identified Summer 2019 scope of work.
    • PBK & American Constructors scheduled for a site investigation on Tuesday 11/20/2018.

     
    November 2, 2018

    • PBK investigating temp kitchen / seating layout. Providing sketch for review on 11/02/2018.
    • PBK providing initial baseball bleacher sketches for KISD review.
    • PBK revising Schematic Design animation video.

     
    October 26, 2018

    • PBK received direction to proceed with presenting Option 3C to the Board of Trustees.
    • PBK provided a study reflecting a mostly interior renovation option for comparison.
    • Option 3C requires the kitchen and cafeteria to be down for an extended period. The team is looking into the logistics of utilizing the Auxiliary Gym as a Cafeteria.
    • PBK will prepare exhibits of possible seating layouts for review. Locations for a serving area will also be included.
    • American Constructors and PBK are to identify scope of work that might be able to be completed in Summer 2019.

     
    October 19, 2018

    • PBK presented 3 Floor plan options with associated cost depicting different ratios and scopes of New Build vs Renovation square footages for district consideration.

    Option 3A:

    • This option works around the classroom wings and the cafeteria and Kitchen.
    • No additional portables needed
    • Cafeteria and kitchen functional throughout the entire construction until new one is built
    • Fine Arts are all in one wing except for the dance studio. Dance studio is an alternate
    • Field House is an alternate

    Option 3B:

    • This option works around the classroom wings to eliminate need for portables
    • Existing Cafeteria and Kitchen will need to be offline during construction of the new one
    • Fine Arts are all in one wing except for the dance studio. Dance studio is an alternate
    • Field House is an alternate

     
    Option 3C:

    • This option pushes the new classroom wing and cafeteria closer to the exiting school
    • Will require demolition of existing classroom wing, Cafeteria and Kitchen all at the same time in order to build the new addition all at the same time
    • Will require portables to replace demolished classrooms
    • Existing Cafeteria and Kitchen will need to be offline during construction of the new one
    • Choir stays where it is existing, and Dance uses existing small gym. Only Theater and Band in the new addition
    • Field House is an alternate: this option has more components in the Field House alternate than the other two options. Included in the alternate are the training room, weight rooms and wrestling room.
    • PBK will further refine option 3C and provide an additional option that is strictly interior renovation.
    • PBK and American Constructors will identify and propose possible areas to be designed and permitted for construction during summer 2019.
    • PBK to propose boring locations for Geotechnical Engineering investigations.

     
    September 28, 2018

    • PBK provided a preliminary massing study of a second design option to facilitate construction phasing and reduce cost. PBK is working on a layout for the corresponding floor plans. This layout will be submitted for KISD’s review by the middle of the week.
    • The consultant’s walk-through field investigation occurred on 9/26/18. The information gathered is currently being compiled.

     
    September 21, 2018

    • Mid Schematic Design presentation to Board of Trustees took place 09/18/2018
    • Construction Manager kick-off meeting with American Constructors took place 09/19/2018

     
    September 14, 2018

    • Schematic Design presentation to KHS staff and student body representatives took place 09/10/2018
    • Schematic Design review meetings with individual departments took place 9/12/2018

     
    September 11, 2018

    • KISD Board of Trustees approved the Construction Manager at Risk ranking.

     
    September 7, 2018

    • Mechanical systems introduction meeting took place 08/31/2018

     
    September 6, 2018

    • Design review meeting with PBK and KISD Facilities.

     
    August 31, 2018

    • City of Killeen introduction meeting took place 08/22/2018.
    • Schematic Design meetings with individual departments took place Tuesday, 08/28/2018.
    • PBK is revising schematic floor plans based on departmental input.

     
    August 17, 2018

    • Second day of the design charrette was concluded on August 16th.
    • Schematic Design meetings with individual departments are to be scheduled in the near future.
    • Following the conclusion of the design charrette, PBK will further evaluate options for the front entry.

     
    August 7, 2018

    • Killeen High School Renovation Construction Manager pre-proposal walkthrough.

     
    July 30, 2018

    • KISD met with PBK for Killeen High School Renovation design charrette and design charrette recap.

     
    July 23, 2018

    • KISD publicly issued a Request for Proposals for Construction Manager at Risk services.

     
    July 12, 2018

    • PBK met with KISD stakeholders at Killeen High School to discuss the renovation space programming.

     
    July 11, 2018

    • PBK met with KISD stakeholders at Killeen High School for departmental space programming review.

     
    July 10, 2018

    • KISD Board of Trustees approved AIA contract with PBK Architects.

     
    June 13, 2018

    • PBK meets with Facility Services to discuss KHS renovation plan concept options.

     
    June 12, 2018

    • KISD Board of Trustees approved PBK Architects as the Architect.
    • KISD Board of Trustees approved Langerman Foster Engineering Company as the Geotechnical and materials testing Engineer.
    • KISD Board of Trustees approved Construction Manager at Risk for the project delivery method.
    • KISD stakeholders meet with PBK Architects for KHS project scope meeting.

     
    June 1, 2018

    • KISD meets with PBK for the Architect and Engineer project kick-off meeting.