ELEMENTARY SCHOOL #36 UPDATES

  • Architect: Huckabee

    Construction Manager: Bartlett Cocke

    Project Delivery Method: Construction Manager at Risk
    Current Phase: Construction
     
    August 7, 2020
    • Site work, site utilities, site paving, underslab utilities, building foundation, CMU, and door frames are in progress.
     
    June 5, 2020
    • Site work, site utilities, and building foundation are in progress.
     
    May 7, 2020
    • Construction has begun. Site setup is in progress and dirt work will start this week.
     
    April 30, 2020
    • The GMP has been approved by KISD Board of Trustees. The project is transitioning into construction.
     
    April 16, 2020
    • Bids have been received and the project is under budget. The GMP is scheduled to be presented to KISD Board of Trustees on April 28th.
     
    March 20, 2020
    • The project is currently bidding.
     
    March 13, 2020
    • Construction Documents are complete. The project is transitioning into the bidding phase.
     
    February 13, 2020
    • Construction Documents are in process.
     
    January 24, 2020
    • Design Development documents are complete. The project is now in the Construction Documents phase.
     
    January 10, 2020
    • Design Development documents are in production.
     
    December 10, 2019
    • Schematic Design approved by KISD Board of Trustees.
     
    December 6, 2019
    • Schematic Design is nearing completion and will be presented to the Board of Trustees on December 10th.
     
    October 11, 2019
    • Schematic Design has begun.
     
    July 9, 2019
    • KISD Board of Trustees approves Command Commissioning, LLC, as the mechanical, electrical, and plumbing commissioning agent. 
     
    July 27, 2018
    • KISD is evaluating options for a potential site for another new elementary school in the district.
     
    July 24, 2018
    • Conference call with Huckabee and Facilities department to discuss preliminary site development.
     
    July 10, 2018
    • KISD Board of Trustees approves Huckabee as the Architect for Elementary #36
    • KISD Board of Trustees approves Rock Engineering as the Geotechnical Engineer and Construction Materials Testing consultant for Elementary #36
    • KISD Board of Trustees approves Construction Manager at Risk as the project delivery method