Architect: Huckabee
Construction Manager: Bartlett Cocke
Project Delivery Method: Construction Manager at Risk
Current Phase: Construction
August 7, 2020
- Site work, site utilities, site paving, underslab utilities, building foundation, CMU, and door frames are in progress.
June 5, 2020
- Site work, site utilities, and building foundation are in progress.
May 7, 2020
- Construction has begun. Site setup is in progress and dirt work will start this week.
April 30, 2020
- The GMP has been approved by KISD Board of Trustees. The project is transitioning into construction.
April 16, 2020
- Bids have been received and the project is under budget. The GMP is scheduled to be presented to KISD Board of Trustees on April 28th.
March 20, 2020
- The project is currently bidding.
March 13, 2020
- Construction Documents are complete. The project is transitioning into the bidding phase.
February 13, 2020
- Construction Documents are in process.
January 24, 2020
- Design Development documents are complete. The project is now in the Construction Documents phase.
January 10, 2020
- Design Development documents are in production.
December 10, 2019
- Schematic Design approved by KISD Board of Trustees.
December 6, 2019
- Schematic Design is nearing completion and will be presented to the Board of Trustees on December 10th.
October 11, 2019
- Schematic Design has begun.
July 9, 2019
- KISD Board of Trustees approves Command Commissioning, LLC, as the mechanical, electrical, and plumbing commissioning agent.
July 27, 2018
- KISD is evaluating options for a potential site for another new elementary school in the district.
July 24, 2018
- Conference call with Huckabee and Facilities department to discuss preliminary site development.
July 10, 2018
- KISD Board of Trustees approves Huckabee as the Architect for Elementary #36
- KISD Board of Trustees approves Rock Engineering as the Geotechnical Engineer and Construction Materials Testing consultant for Elementary #36
- KISD Board of Trustees approves Construction Manager at Risk as the project delivery method