CLIFTON PARK & BELLAIRE CONSOLIDATED ELEMENTARY SCHOOL UPDATES

  • Architect: Huckabee
    Architect’s Consultants:
    Civil Engineering & Surveying: Kimley- Horn
    Technology/ Security: Crux Solutions
    MEP Engineering: IEG
    Food Service: FDP
    Construction Manager: Cloud Construction
    Geotechnical Engineer: Langerman Foster
    Commissioning Agent: Encotech
    Project Delivery Method: Construction Manager at Risk
    Current Phase: Construction
     
     
    March 13, 2021

    • The project is substantially complete. Punch list work is on-going.

     
    January 8, 2021

    • Final miscellaneous interior and exterior work is in progress. The project is close to completion.

     
    April 30, 2020

    • Roofing, waterproofing, insulation, windows, exterior veneer, metal stud framing, and door frames in process.

     
    April 16, 2020

    • ICF, CMU, waterproofing, structural steel, upper level slabs and site utilities in process.

     
    January 10, 2020

    • Grade beams, building slab, site utilities, and under slab utilities in process.

     
    May 17, 2019

    • The Board of Trustees approved the Guaranteed Maximum Price. The project is transitioning into construction.

     
    May 9, 2019

    • Bids have been received and the project is under budget. Cloud Construction is currently compiling the Guaranteed Maximum Price.

     
    March 28, 2019

    • Bid documents are complete and the project is out for bidding.

     
    March 7, 2019

    • 100% quality control page turn with Huckabee and KISD Facilities.
    • Clifton Park bidding/ construction strategy discussion with Huckabee and KISD Facilities.

     
    March 5, 2019

    • KISD Board of Trustees approves contract with Encotech for Commissioning services.

     
    February 11, 2019

    • The project has transitioned from the Design Development phase to the Construction Document phase and is currently on schedule.
    • Cost estimates have been completed for the Design Development phase and the project is currently estimated to be under budget.
    • Exterior stone and brick color options were presented to district leadership on February 5th and selections were made.
    • Interior finish options were presented to district leadership on February 5th and selections were made.

     
    January 25, 2019

    • Construction coordination meeting with Huckabee, Cloud Construction, and KISD Facilities.

     
    January 24, 2019

    • The design team met with stakeholders on January 10th and the Principals on January 16th to review the site plan, floor plans, and detailed documents, and they provided valuable input.

     
    January 13, 2019

    • At the December Board Meeting, the Board of Trustees approved a change to the exterior design of the prototype building to be more equitable to the most recent KISD school designs.
    • Design Development documents are in production.
    • The design team met with all stakeholders to review the documents and provided valuable input.
    • The construction manager for the project, Cloud Construction, has been providing input to the design team on constructability and cost management.

     
    January 12, 2019

    • KISD Board of Trustees approves Encotech as the commissioning agent.

     
    January 9, 2019

    • KISD Board of Trustees terminates the lease agreement with American Towers, LLC.

     
    December 12, 2018

    • Huckabee presented Schematic Design to City of Killeen.

     
    December 11, 2018

    • KISD Board of Trustees approves the Schematic Design.
    • KISD Board of Trustees approves the Construction Manager at Risk ranking order, with Cloud Construction as the top ranked Construction Manager.

     
    November 30, 2018

    • Schematic Design was presented to the Board of Trustees on Tuesday. Board members provided valuable feedback and expressed positive support for the design of the building. The project goes to the Board on December 11th for approval of the Schematic Design phase.
    • The proposals for Construction Managers have been received and are currently under evaluation.

     
    November 26, 2018

    • Campus meeting with Huckabee, KISD Facilities, and Principals to discuss consolidation.

     
    November 13, 2018

    • KISD Board approves an amendment to the existing Huckabee contract, which was previously approved for other Bond projects, to include the Clifton Park / Bellaire Elementary School Consolidation project in their scope of services.
    • KISD Board approves an amendment made to the existing Langerman Foster contract, which was previously approved for other Bond projects, to include the Clifton Park / Bellaire Elementary School Consolidation project in their scope of services.

     
    October 30, 2018

    • Construction Manager pre-proposal site walk.

     
    October 22, 2018

    • KISD publicly issued a Request for Proposals for Construction Manager at Risk services.

     
    October 9, 2018

    • KISD Board of Trustees approves Huckabee as the Architect and Langerman Foster as the Geotechnical Engineer.

    KISD Board of Trustees approves the Construction Manager at Risk project delivery method.