- Killeen ISD 2018 Bond
- DESIGN UPDATES
EAST WARD & WEST WARD CONSOLIDATED ELEMENTARY SCHOOL UPDATES
-
EAST WARD & WEST WARD CONSOLIDATED ELEMENTARY SCHOOL UPDATES
Architect: Huckabee
Architect’s Consultants:
Civil Engineering & Surveying: Kimley- Horn
Technology / Security: Crux Solutions
MEP Engineering: IEG
Food Service: FDP
Contractor: Bartlett Cocke Construction
Geotechnical Engineer: Arias and Associates
Commissioning Agent: Command Commissioning
Project Delivery Method: Construction Manager at Risk
Current Phase: Construction
May 1, 2021- The project is complete.
February 13, 2021- The project is nearly substantially complete. Punch list work to start in the next week or two.
February 12, 2021- Final miscellaneous interior and exterior work is in progress. The project is close to completion.
April 16, 2020- Metal stud framing, waterproofing, insulation, roofing, spray-on fireproofing, and door frames in process.
January 10, 2020- Structural steel, metal decking, upper level slabs, CMU, MEP rough-in, and site utilities in process.
June 11, 2019- KISD Board of Trustees approved the Guaranteed Maximum Price contract with Huckabee.
May 17, 2019- The project has completed the bidding process and is under budget by $1,713,503. Bartlett Cocke Construction is currently compiling the Guaranteed Maximum Price.
May 9, 2019- Bid documents are complete and the project is out for bidding.
April 11, 2019- 100% Construction Documents progress review/page turn with Huckabee and KISD Facilities.
March 28, 2019- 100% quality control documents have been completed and are currently under review by KISD.
March 7, 2019- 50% Construction Documents progress review/ page turn with Huckabee and KISD Facilities.
March 5, 2019- KISD Board of Trustees approved task request with Command Commissioning to provide MEP commissioning services.
- KISD Board of Trustees approved contract amendment with Kleinfelder for construction materials testing services.
February 12, 2019- KISD Board of Trustees approves selection of Command Commissioning as the Commissioning agent.
February 11, 2019- The project has transitioned from the Design Development phase to the Construction Document phase and is currently on schedule.
- Cost estimates have been completed for the Design Development phase and the project is currently estimated to be under budget.
February 8, 2019- Second move out coordinating meeting for East Ward and West Ward.
January 24, 2019- The design team met with all stakeholders, including the Principals, on January 17th to review the site plan, floor plans, and detailed documents.
January 15, 2019- East Ward and West Ward move out coordination meeting.
January 13, 2019- Design Development documents are in production.
- The Construction Manager for the project, Bartlette Cocke Construction, has been providing input to the design team on constructability and cost management.
December 12, 2018- Huckabee presented Schematic Design to City of Killeen.
December 11, 2018
- KISD Board of Trustees approved the Construction Manager at Risk rank order, with Bartlett Cocke as the highest ranked Construction Manager.
November 30, 2018- The design team continues to refine the project design and work through big picture details of the site and floor plans.
- The selection of the Construction Manager for the project is slated to go to the Board of Trustees on Dec. 11th. The district has chosen the Construction Manager at Risk project delivery method which means the contractor will be on board during design and will provide valuable input to the design team on constructability and cost management.
- Geotechnical borings and analysis are complete, and the report has been received from the engineer.
October 9, 2018- KISD Board of Trustees approves the Schematic Design.
September 28, 2018- The design team presented the Schematic Design package to the Board of Trustees. Board members provided valuable feedback and expressed strong support for the design of the building.
September 14, 2018- The design team met with District leadership to review options and determine a palette for the interior materials and colors.
September 9, 2018- Schematic Design technology departmental review with Huckabee and KISD Facilities.
September 7, 2018- The design team met with several stakeholder groups over several days to share the latest version of the design and receive input.
- A draft version of the Schematic Design documents were delivered to KISD on 9/6/18.
September 5, 2018- KISD committee gathered and ranked the Construction Manager at Risk proposals.
August 15, 2018- Huckabee introduce/ present project concepts to City of Killeen staff.
August 14, 2018- KISD Board approved the Geotechnical Engineer contract with Kleinfelder.
August 9, 2018- Initial site plan and floor plan concepts were reviewed with KISD staff and Huckabee on Tuesday. The feedback was very positive with a few requested changes that are easily incorporated.
- The design team has transitioned to developing massing and 3-dimensional concepts.
August 2, 2018- Initial concepts for the building and site plans are nearly complete ahead of a planned meeting with KISD leadership next week.
July 27, 2018- Huckabee design team is generating site plan and floor plan concepts for a 3-story design solution
- Huckabee team is evaluating drainage patterns and existing underground utilities on/around the existing property to determine the best option for managing stormwater.
July 23, 2018- KISD publicly issued a Request for Proposals for Construction Manager at Risk services.
July 19, 2018- KISD stakeholders meet with Huckabee for 2018 Bond projects owner kick off meeting.
July 10, 2018- KISD Board of Trustees approves contract with Huckabee.
June 14, 2018- Meeting with Facilities department, campus Principals and leadership to discuss transition planning.
June 13, 2018- KISD stakeholders meet to discuss the transition planning for East Ward & West Ward consolidation.
June 12, 2018- KISD Board of Trustees approves Huckabee as the Architect.
- KISD Board of Trustees approves Construction Manager at Risk as the project delivery method.
- KISD Board of Trustees approved The Kleinfelder Group as the Geotechnical Engineer and materials testing Engineer.